Define the purpose and measurement boundaries
Do you want to compare consumption between lines, investigate demand outside production hours or calculate energy per product batch? The answer determines the measurement points, data and reports required. We first identify the loads included in each measurement, then select meters and plan the integration.
A meter on the supply to an entire hall also measures shared loads, such as ventilation or compressed air equipment. Its readings do not represent the consumption of one machine. With meters at several levels, the reporting model must also avoid counting the same energy twice by adding a main meter to its submeters.
We match the scope of energy monitoring to the decisions the plant intends to make using the measurements.
Verify the measurement chain first
Before commissioning reports, we check the measurement arrangement, phase assignments, direction of energy flow and configured current and voltage transformer ratios, where applicable. Incorrect settings can produce plausible values that do not reflect actual consumption.
We establish whether communication registers already contain values referred to the primary side. Applying the transformer ratio again in the supervisory system will overstate the result. We compare acquired values with the meter display for the same quantity, unit and measurement time or period.
Distinguish power, counter readings and consumption
Active power in kW and active energy in kWh answer different questions. Energy over a period can be calculated from the increase in the appropriate cumulative counter. For example, an imported-energy reading increasing from 12,500 kWh to 12,800 kWh represents 300 kWh imported at that measurement point, provided the counter was not reset, rolled over or replaced between the readings. Where the plant has its own generation, grid imports alone do not represent its total consumption.
The maximum instantaneous power reading is different from the maximum average demand over a defined interval. If a report is intended to monitor billing demand, the averaging method and interval boundaries must match the applicable billing arrangement. Polling a meter frequently does not automatically reproduce that measurement.
Agree the acquisition method and data quality rules
For Modbus TCP or RTU integration, we check the register map for the specific meter: addresses and read functions, data types, word order, units and scaling. We also establish whether each value represents imported, exported or net energy. These quantities are not interchangeable.
- Store each reading with its measurement point identifier, timestamp and validity and freshness information.
- Select the polling interval to suit the report, the meter and the communications bus.
- Mark communication failures as missing data; do not present the last valid reading as a fresh measurement.
- Handle resets, rollovers and replacements explicitly for cumulative import and export counters. A net energy value can legitimately decrease, so interpret it according to the manufacturer's definition.
After a communication outage, the next valid counter reading may allow the total consumption over the gap to be recovered, provided the meter continued counting correctly. It does not show how that energy was distributed between shifts or batches. Reconstructing that profile requires suitable history in the meter or another logger, if available.
Link energy to actual production
Shift reports, consumption outside production hours and energy per unit of product require a consistent time basis. We agree clock synchronisation, time zones, shift boundaries and handling of daylight saving time changes.
A kWh-per-unit or kWh-per-tonne indicator needs production output data and comparable operating conditions. Start-up, downtime, cleaning and product changes can affect the result. Shared utilities are not allocated to one line without an agreed allocation method. Linking meter data to PLC or MES information requires OT/IT integration and consistent machine and batch identifiers.
Verify the measurement before assessing savings
During acceptance checks, we compare meter and report energy increments, verify units and flow direction, and check behaviour after communication loss and restart. Monitoring shows where and when energy is used. Savings are assessed after specific changes have been implemented, using comparable data; a graph alone does not demonstrate savings.
Technical documentation
The relevant meter manual defines how its measurements should be interpreted. Manufacturer examples from Schneider Electric cover transformer configuration, demand calculation and measurement data logging. We confirm the available functions and data formats for the devices installed at the plant.